This system was established with Environment Protection and Infrastructure Operational Programme in 2006
Description of project:
4 pc heat pumps (Aermec NW 0601)
120 pc BHEs with 100 m depth
32 mm-diameter pipe
10 m distance between BHEs
Heat demand: 610kW
We examine the change of ground temperature around the BHE field to ensure sustainability!